Las Vegas Sands has all the money they need
Bloomberg has an article today saying that Las Vegas Sands has “all the money required to be able to complete the project.” And thanks to the global economic slowdown, according to the raw materials pipeline is finally starting to open up, which should alleviate some of the hurdles the company has faced during the construction.
And the timeline:
Las Vegas Sands expects to open at least 1,000 hotel rooms in two towers on schedule by the end of 2009, Executive Vice President Bradley Stone said Nov. 10. The company will also open “a portion” of the mall, the casino, and most of Marina Bay Sands’ meeting and conference space, he said.
Hotel, Mall
By mid-2010, Las Vegas Sands plans to open the remaining hotel rooms and most of the mall, with final stages such as a sky park and some suites possibly taking longer, Stone said.